Welcome to ECVERY
FR25-21 tube straightening machine,High Precision Steel Hydraulic forming machine
FR25-21 tube straightening machine,High Precision Steel Hydraulic forming machine
Supplier Info
[China Supplier]
Contact Person : Ms. Chou Shelly
Tel : 86-769-83202641
Fax : 86-769-83126559
Product Detail
Hydraulic forming machine 1.Lower noise and durable. 2.Ultra-precision under 0.05mm 3.Diamater:8-25mm

FR25-21 tube straightening machine,High Precision Steel Hydraulic forming machine

Straightening Maximum diameter25mm
Straightening the minimum diameter8mm
Roller group number10 groups
Total power3KW
Weight800KG
 Size1100 * 900 * 950mm

Straightening machine is straightening for metal bar, pipe, wire and other equipment. Straightening machine changes straightness by the straightening roller squeezing on the bar, etc, generally, there are two rows of straightening rollers and numbers different.  There are also two roller straightening machines to straighten the material of different diameters, which rely on two roller (middle concave, hyperbolic roll) of.

The main types has:  pressure straightening machine, balance roller straightening machine, shoes roller straightening machine, rotating anti-straightening machine and so on

Straightening machine and process equipment from Da Lang Fang Rong Machinery Factory, established in 2000, is a professional design, manufacturing, non-ferrous metals and ferrous metal tube, rod, row, and wire production line equipment manufacturers, the main products are straightening machine, drawing machine, chickened machines , rolling machine. Established the whole series lines equipment from drawing, straightening, polishing, until to the finished production according to customer requirements, the design concepts is to design, manufacturing equipment based on customer demand

  

steel pipe making machine,metal pipe straightening machine,machinery manufacturer

Quality Process Certifications: ISO 9000-2001 

Quality guarantee:

 (1) Factory guarantees machinery well packed and testing qualified before shipment. 

 (2) Factory guarantees all the goods are brand-new; no defects for the specifications or materials used. Twelve months quality warranty after Customer accepts the inspection for machinery’s trial operation.

Claims

Customer has rights to claims if there is quality problem caused by deficient manufacturing procedure, material or technical parameter, which doesn’t match the contract specified, factory will take responsibility for all related expenses caused.

Penalty

1, if contractual delivery day postponed due to factory’s reason except force-majeure, Customer has rights to get the compensation by portion from factory based on the followings:

(1)   factory has ten days grace period

(2)   Starting from the eleven days after delivery day postponed, every day’s penalty for factory is the whole contract amount’s 0.1%.

2, if contractual payment day postponed due to Part A’s reason except force-majeure, factory has rights to get the compensation by portion from Customer based on the followings:

(1)    Customer has ten days grace period

(2)   Starting from the eleven days after payment day postponed, every day’s penalty for Customer is the whole contract amount’s 0.1%.

3, the above mentioned penalty total amount can not be exceeding the whole contract amount’s 5%.

Force Majeure:

We factory shall not be held responsible for late delivery of the goods owing to generally recognized Force Majerue. Factory should notice Customer by oral immediately. 15 days later after force Majerue happens, and post customer the written proof documents from the related departments. If force manjerue keeps more than 60 days, Customer can cancel the contract. Factory should return the payment.

Technical materials provide:

Factory should provide the following data

Each of Chinese / English version manual and matching tools enclosed for one machine.

Contract amendment

Any changes for the contract clauses, a written contract amendment must be signed by both parties.

Arbitration

If there is dispute during contract implementation, we should settle through  negotiation made in the principle of fair cooperation. If not, the case under dispute shall be submitted for arbitration. Which has the same equally binding to both Parties, The cost of arbitration shall be borne by the losing party. During the arbitration, the non-dispute portion of the contract continues to implement except the arbitration part.

FR25-21 tube straightening machine,High Precision Steel Hydraulic forming machine

Ads by Google

About Us | Contact Us | Help | Terms & Conditions
Hot Products: A | B | C | D | E | F | G | H | I | J | K | L | M | N | O | P | Q | R | S | T | U | V | W | X | Y | Z | 0-9
Copyright Notice @ 2008-2022 ECVERY Limited and/or its subsidiaries and licensors. All rights reserved.